The timeline of the overall reporting (both partner-level and project-level) until the approval of a Project Report will vary depending on the speed of certain steps of certain actors within the process. However, considering the deadlines, in normal case the approval of a Project Report and the following payment of reimbursement can be planned for the 4th-5th months counted from the end of the Reporting period.